A short week, following the four day Easter long weekend, but a long list of items ticked off the list!
- waterproof enclosure for outdoor area audio-visual and low voltage equipment mounted to wall (DIY by me
) - wiring at main switchboard almost complete
- painting now ~85% complete
- light installed above shaving cabinet in downstairs bathroom
- security lighting installed at side of the house and on wall overlooking outdoor area
- second weatherproof power outlet installed in outdoor area below the A/V gear box
- new light fittings installed in dining room and front bedroom
- oven and dishwasher installed
- upstairs toilet finished
- cabinetry finished in upstairs bathroom
- feature wall (brightest purple you will ever see
) painted in outdoor area - downstairs toilet finished
- spill lighting installed at top of the new storage units upstairs
- bedroom wall (previously water-damaged) repaired and repainted
- floorboard repairs underway